Transmission Services
Diversified's transmission construction experience covers all aspects of wood and steel structure erection, re-conductoring and re-insulation projects. Our crews are experienced in construction work in environmental sensitive landscapes. We have worked with several state and federal agencies to assure that ESA and other environmental concerns are always addressed in a manner satisfactory to our client.
Examples of Previous Projects:
PG&E Transmission Project
- Diversified replaced 2,023 shunt splices on 230kv lines using helicopters exclusively for this project. These six circuits crossed the San Francisco Bay where access was not possible due to sensitive environments.
- Built 2 miles of new 115kv line in Fresno County.
- Installed tower guards and high voltage signs on various PG&E tower lines.
Southern California Edison Transmission Project
- Provided wind-storm response crews to replace more than 50 transmission poles after a devastating storm in Orange County.
- Replaced poles and conductor on 20 miles of 69kv with 12kv under-builds on a major highway right-of-way in Tulare County.
- Installed steel pole in 230kv substation, transferred conductors over energized station and added new spans to station rack.
- Remove 25 115kv steel transmission towers on limited access state park land.
Nevada Power Corporation Project
Up grade 21 - 138kv line sections and install new 138 kv lines in Las Vegas, Nevada including crossings of Interstate 15 in the downtown area. Replace thirty circuit miles of 954 ACSR with 954 SAC. Diversified installed pole foundations, set steel poles and reconductored existing lines having 230kv overbuild.
Install five miles of 230kv double circuit with 138kv underbuild. In addition reconductor ten miles of existing 230kv line.
Diversified also installed twenty miles of OPGW and ADSS fiber optic cable. The latest in pulling equipment was utilized including the Condux AFB 506 tensioner , the FBR 518 hydrolic tensioner and Condux reel trailers. Other work included installing substation duct banks and pulling 145 kv 2000 mcm Copper UG cable.
San Diego Gas and Electric Project
During the 2007 Southern California wildland fires Diversified provided twenty five line crews to assist SDG&E replace both transmission and distribution lines.
In 2010 Diversified replaced 21 wood transmission poles with steel structures and transferred 12kv underbuild.
Sacramento Municipal Utility District Project
In 2008 Diversified crews resaged fourty miles of 230Kv line conductors.
In 2009 Diversified completed an 18 miles 23kv bundling and re-insulation project.
Western Area Power Administration
Diversified recently completed building a sixteen mile
60Kv transmission line insulated for 115kV, and switching station
for WAPA in the Weaverville area of Northern California. The project
includes overseeing R/W clearing, access road construction and erosion
control.